Assignment relates to scheduling in project management.

Question 1: Given the activity below. please draw an activity-on-arrow network on page 4.

Activity Predecessor Duration
A --- 1
B --- 4
C --- 3
D A 2
E A 3
F C 3
G B, C 4
H D, B 4
I E 2
J F, G 2
K F, G 3
L F, G 2
M L 2
N H, I 1
O H, I 2
P J, N 3
Q K, P 3
R K, U 2
S K, U 1
T M 2
U M 3
V T 1
W V 1
X S, T, W 2
Y Q 2
Z O 2

Question 2: Given the sub networks below, follow all conventions used in class and calculate the four activity times for Activity B. No splitting allowed.

184_Figure.jpg

Question 3:  Given the sub networks below, follow all conventions used in class and calculate the four activity times for Activity B. No splitting allowed.

586_Figure1.jpg

Question 4: Calculate the schedule on the next page for the case of no splitting. Complete the forward pass and start the backward pass and place your answers in the table.

359_Figure2.jpg

Question 5: Calculate the schedule on the next page for the case of no splitting. Complete the forward pass and start the backward pass and place your answers in the table.

Activity
ID

Early
Start

Early
Finish

Late
Start

Late
Finish

Float

A

1

10

 

 

 

B

14

21

 

 

 

C

11

30

 

 

 

D

 

 

 

 

 

E

11

19

 

 

 

F

 

 

30

43

 

G

 

 

45

46

 

H

 

 

47

52

 

I

 

 

37

39

 

J

 

 

 

 

 

Request for Solution File

Ask an Expert for Answer!!
Project Management: Draw an activity-on-arrow network - given the sub networks
Reference No:- TGS01519975

Expected delivery within 24 Hours