Assignment relates to scheduling in project management.
Question 1: Given the activity below. please draw an activity-on-arrow network on page 4.
| Activity |
Predecessor |
Duration |
| A |
--- |
1 |
| B |
--- |
4 |
| C |
--- |
3 |
| D |
A |
2 |
| E |
A |
3 |
| F |
C |
3 |
| G |
B, C |
4 |
| H |
D, B |
4 |
| I |
E |
2 |
| J |
F, G |
2 |
| K |
F, G |
3 |
| L |
F, G |
2 |
| M |
L |
2 |
| N |
H, I |
1 |
| O |
H, I |
2 |
| P |
J, N |
3 |
| Q |
K, P |
3 |
| R |
K, U |
2 |
| S |
K, U |
1 |
| T |
M |
2 |
| U |
M |
3 |
| V |
T |
1 |
| W |
V |
1 |
| X |
S, T, W |
2 |
| Y |
Q |
2 |
| Z |
O |
2 |
Question 2: Given the sub networks below, follow all conventions used in class and calculate the four activity times for Activity B. No splitting allowed.

Question 3: Given the sub networks below, follow all conventions used in class and calculate the four activity times for Activity B. No splitting allowed.

Question 4: Calculate the schedule on the next page for the case of no splitting. Complete the forward pass and start the backward pass and place your answers in the table.

Question 5: Calculate the schedule on the next page for the case of no splitting. Complete the forward pass and start the backward pass and place your answers in the table.
|
Activity ID
|
Early Start
|
Early Finish
|
Late Start
|
Late Finish
|
Float
|
|
A
|
1
|
10
|
|
|
|
|
B
|
14
|
21
|
|
|
|
|
C
|
11
|
30
|
|
|
|
|
D
|
|
|
|
|
|
|
E
|
11
|
19
|
|
|
|
|
F
|
|
|
30
|
43
|
|
|
G
|
|
|
45
|
46
|
|
|
H
|
|
|
47
|
52
|
|
|
I
|
|
|
37
|
39
|
|
|
J
|
|
|
|
|
|