Draw an a on a chart find the critical path and the project


Question A

A project is made of 7 activities:

Activity

Initiation

Analysis

Data Modeling

Process Modeling

Design

Feasibility Analysis

Documentation

a

14

14

3

1

2

4

5

b

18

34

11

1

4

12

15

m

16

15

4

1

3

5

13

Predecessors

--

--

Analysis

Analysis

Data and Process Modeling

Data and Process Modeling

Initiation and Analysis

  1. Draw an A on A chart.
  2. Find the critical path and the project duration.

Question B

A project is made of 8 activities:

Activity

A1

A2

A3

A4

A5

A6

A7

A8

Duration

20

13

15

9

20

30

20

25

Pre. Activity

-

-

-

A2

A1,A3,A4

A1,A3,A4

A5,A6

A6

  1. Draw an A on A chart.
  2. What is the critical path? What is the project duration?
  3. When the latest can we start activity A1?
  4. When the latest can we start activity A5?
  5. Refer to the critical path you found in b. Assume that every activity is normally distributed. Each activity's mean is given in the table above. Each activity's standard deviation is 20% of its mean (for example, the mean duration of activity A2 is 13 and its standard deviation is 2.6). What is the probability that the project will last more than 80 days?

Question C

Complete the following table:

slack

LF

LS

EF

ES

Predecessor(s)

Duration

Task

 

 

 

 

 

-

5

A

 

 

 

 

 

-

10

B

 

 

 

 

 

A

20

C

 

 

 

 

 

A,B

13

D

 

 

 

 

 

C,D

10

E

 

 

 

 

 

A,B

25

F

 

 

 

 

 

E,F

8

G

Solution Preview :

Prepared by a verified Expert
Business Management: Draw an a on a chart find the critical path and the project
Reference No:- TGS01118060

Now Priced at $30 (50% Discount)

Recommended (98%)

Rated (4.3/5)