Draw activity-on-node diagram and identify activity duration


Problem:

Question 1) Draw an Activity-on-Node Diagram, identify activity duration, slack for each activity, project duration, and project critical path for the following:

Activity Name

Predecessor(s)

a

m

b

A

None

5

30

40

B

None

10

20

50

C

None

5

15

30

D

A

5

10

30

E

B,C

15

20

25

F

C,D

15

20

60

G

F

10

20

50

Solve the problem and show all work.