Draw a pert network for the problem


Task: A project is characterized by activities A through F. The predecessor activities and the times required, and costs for both a regular and crash program for each activity are shown in the attached table.

a. Using only the time for the regular program activities, draw a PERT network for this problem. What is the critical path? How long will it take to complete the total project?

I believe the critical path is A, B, E and it will take 9 days to complete the project but I am not sure this is correct.

b. What is the cost of the project as given in a. (I believe the cost is $32,000)

c. Find the time-cost trade-off points that are possible. What is the minimum time in which the project can be completed? What is the cost of this program?

Activity

Predecessor Activities

Time/Weeks

Regular

Crash

Cost (000's)

Reg.

Cost (000's)

Crash

A

None

0

-

0

-

B

A

5

3

10

22

C

A

2

1

6

15

D

B, C

3

2

6

15

E

B

4

2

10

25

F (finish)

D, E

0

-

0

-

Solution Preview :

Prepared by a verified Expert
Basic Statistics: Draw a pert network for the problem
Reference No:- TGS01864406

Now Priced at $25 (50% Discount)

Recommended (94%)

Rated (4.6/5)