Draw a network for the project using for the immediate


Question: Consider the following project.

641_AP.png

1. Draw a network for the project using for the immediate predecessors.

2. Calculate the expected activity times for all the activities.

3. List All unique paths from start to finish and the path duration of the paths.

4. What is the project completion time and the critical activities?

5. Develop the earliest and latest start and finish times and the stack time for all the activities.

6. Calculate the variance and standard deviation of the project completion time.

7. What is the probability that the project will be late if the due date is 40 weeks?

8. What is the probability that the project will be late if the due date is 25 weeks?

9. Determine the chat date if the desired probability of completing the project on time is 96%.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Draw a network for the project using for the immediate
Reference No:- TGS02653933

Expected delivery within 24 Hours