Draw a network for the project using aon method


Problem:

A project is composed of 8 tasks. The three-time estimates (in days) for each activity plus the precedence requirement for each are shown in the table below:

Activity    Activity Time Estimates
(in days)    ImmediatePredecessor
A    2, 3, 4    None
B    3, 4, 11    None
C    1, 2, 3    A, B
D    4, 5, 12    C
E    3, 5, 7 C
F    2, 3, 4    E
G    2, 3, 10    C
H    2, 3, 4    D, G, F
I    2, 3, 10    D, F
J    1, 2, 3    H
K    1, 2, 3    I, J

Q1. Draw a network for the project using AON method.

Q2. Determines the critical path(s) and identify them by a) double lining the arrows connecting the activities on the CP (like ===) AND

Q3. Writing the letter representing the activities on the CP in the answer-sheet-set.

Q4. Do a complete path analysis and fill the table in the answer-sheet set

Q5. What are the chances that the project will finish within 25 days?

Q6. What are the chances that the project will take longer than 23 days to finish?

Solution Preview :

Prepared by a verified Expert
Project Management: Draw a network for the project using aon method
Reference No:- TGS01954161

Now Priced at $25 (50% Discount)

Recommended (99%)

Rated (4.3/5)