Draw a network diagram for the building of the summerhouse


Doris and Dennis Datcher, experts at DIY, want to build a summerhouse in their garden. They will start by drawing up a proper plan, which they can complete in 2 days. Once they have a plan they can prepare the site, which will take 6 days, order the timber, which will be delivered in 10 days from placing the order, and purchase the ironmongery, which will take 2 days. Once they have the timber and ironmongery they can construct the floor panels, which will take 4 days, make the frames for the walls, which will take 2 days, and construct the door, which will take 1 day. When they have made the wall frames they can board them up, which will take 2 days. When they have prepared the site and constructed the floor panels they can lay the floor, which will take 1 day. As soon as the floor is laid and the wall frames boarded they can erect the walls, which will take 1 day. Once the walls are erected the roof joists can be fixed, which will take 2 days. Having fixed the roof joists the roof can be boarded and weatherproofed, which will take 4 days. Once the door has been constructed and the walls erected they can hang the door, which will take 1 day.

(a) List the activities involved in building the summerhouse and identify the predecessor activities for each of them as well as their durations.

(b) Draw a network diagram for the building of the summerhouse and from it identify the critical path and the minimum duration of the project.

Request for Solution File

Ask an Expert for Answer!!
Chemical Engineering: Draw a network diagram for the building of the summerhouse
Reference No:- TGS02203510

Expected delivery within 24 Hours