Draw a network diagram for the activities construct a gantt


Assignment

Weekly topics: Expected time for activities/ Outline of an information systems plan

I: Time estimates

Calculate the expected time for the following activities.

Activity

Optimistic Time

Most Likely Time

Pessimistic Time

Expected Time

A

3

7

11


B

5

9

13


C

1

2

9


D

2

3

16


E

2

4

18


F

3

4

11


G

1

4

7


H

3

4

5


I

2

4

12


J

4

7

9


II: Project diagrams

A project has been defined to contain the following list of activities along with their required times for completion.

Activity No.

Immediate Activity

Time (weeks)

Predecessors

1

Collect requirements

3


2

Analyze processes

2

1

3

Analyze data

2

2

4

Design processes

6

2

5

Design data

3

3

6

Design screens

2

3,4

7

Design reports

4

4,5

8

Program

5

6,7

9

Test and document

7

7

10

Install

2

8,9

Specific tasks for exercise II project diagrams.

1. Draw a network diagram for the activities.
2. Construct a Gantt chart for the project.
3. Calculate the earliest expected completion time.
4. Show the critical path.

III. Preliminary outline of an information systems plan

• Create a preliminary outline of an information systems plan.

• Choose a company that you are familiar with (or research one that you are note).

• Follow the "Outline of an information systems plan" shown in and complete a short information systems plan for the organization you chose.

• Write at least one brief paragraph for each of the seven categories in the outline.

FIGURE 4-15 Outline of an information systems plan

Located in: Hoffer, J, George, J, Valacich, J (2016). Modern Systems Analysis and Design. Upper Saddle River, NJ. Prentice Hall.

Solution Preview :

Prepared by a verified Expert
Management Information Sys: Draw a network diagram for the activities construct a gantt
Reference No:- TGS02446647

Now Priced at $40 (50% Discount)

Recommended (95%)

Rated (4.7/5)