Draw a network diagram and show the critical path


Given the following information, draw CPM diagram:

Activity Immediate Predecessor Duration (Days)

1 - 5
2 - 3
3 1, 4 2
4 2 6
5 2 5
6 3, 5 3

a) Draw a network diagram and show the critical path.

b) What is the earliest time, the above project can be completed?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Draw a network diagram and show the critical path
Reference No:- TGS077828

Expected delivery within 24 Hours