Draw a gantt chart for this project what is the project


A construction company requires the following activities for a project:

Activity

Immediate Predecessor

Activity time

A

None

5

B

None

2

C

B

7

D

A, C

2

E

B

6

F

D

6

G

E

5

a. Draw a Gantt chart for this project

b. What is the project completion time?

c. Draw a activity on node network for this project

d. Make a forward pass and a backward pass to determine ES, LS, EF and LF for all activities

e. What is the critical path?

f. Propose a plan to reduce the project duration by 2 days.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Draw a gantt chart for this project what is the project
Reference No:- TGS01089321

Expected delivery within 24 Hours