Draw a gantt chart for the tasks


Discuss the below:

Q: Assume you have a project with seven activities Labeled A-G, as shown below. Derive the earliest completion time (or early finish time - EF), the latest completion time (or late finish - LF) and slack for each of the following tasks (begin at time =0).

Which tasks are on the critical path? Draw a Gantt Chart for these tasks. Draw a Network Diagram for the tasks. Highlight the critical path. Even guidance on drawing Gantt Chart and Network Diagram will do.

Task preceding Event Expected Duration
A - 5
B A 3
C A 4
D C 6
E B,C 4
F D 1
G D,E,F 5