Assignment- Critical Path Diagram
For a project with the following tasks, durations, and task precedence data:
• Draw a Critical path diagram. Sometimes referred to as PERT or a CPM diagram.
• How long will the project take to complete.
|
|
Task Description
|
Duration (days)
|
Preceding Task
|
|
1
|
Requirements Collection
|
5
|
-
|
|
2
|
Screen Design
|
6
|
1
|
|
3
|
Report Design
|
6
|
1
|
|
4
|
Database Design
|
2
|
2,3
|
|
5
|
User Documentation
|
5.5
|
4
|
|
6
|
Programming
|
5
|
4
|
|
7
|
Testing
|
3
|
6
|
|
8
|
Installation
|
1
|
5,7
|