Do a network diagram and a pdm for this project do a


CASE STUDY: CONSTRUCTION

Craig Construction: Home Improvement Project

Having completed the quality planning of the project, Nash wanted to set the expectations of schedule performance with Craig. He asked Craig, "What is the order in which you are planning to do the job?"

Craig answered, "Let's see...I will write down the activities for you."

Nash asked Craig to let him know the order in which the activities had to be completed. Craig took out paper and started writing down the activities with their duration& He wrote which of the activities would take precedence over the others.

Nash looked at the list and asked Craig, "So the only activities that can be done at the same time are the window installation and the roof and sky-light installation?"

Craig replied, "Yes."

Nash entered all this information into Microsoft Project.

Case Questions

1. Input all the information provided by Craig into Microsoft Project.

2 Do a network diagram and a PDM for this project.

3. Do a scenario analysis for the installation of windows lasting four days.

4. If Craig hires one more person for $80 a day and tries to bring back the installation to three days, what is the crash cost?

5. How can you fast-track this project? How many days can you save by fast tracking?

Solution Preview :

Prepared by a verified Expert
Project Management: Do a network diagram and a pdm for this project do a
Reference No:- TGS01374034

Now Priced at $35 (50% Discount)

Recommended (92%)

Rated (4.4/5)