Discussion question dq2 chapter 4 of designing and managing


Discussion question DQ2 Chapter 4 of designing and managing the supply chain of simchi levi 3rd edition. Manufacturer Sells electricity for $20. They can buy it from 1 of 2 suppliers. Supplier 1 is a fixed contract and sells to the Manufacturer for $10. Supplier 2 is an option contract with $6 reservation price and $6 once product is delivered. Assume 6 months before demand is realized a contract must be signed. Contracts are assigned in February and Demand is realized in 10 weeks starting in August. There are 0 inventory costs and unsold items after 10 weeks have 0 value. What is the Best Procurement Strategy?

Probability Table

Demand   800   1000   1200   1400   1600   1800

Prob   0.11   0.11   0.28   0.22   0.18 

0.1

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Discussion question dq2 chapter 4 of designing and managing
Reference No:- TGS01102590

Expected delivery within 24 Hours