Discussion about breaching the contract


Assignment task:

Hugh Turne signed a contract to purchase 50 acres of residential land from Norman Conquest.  Hugh planned to build a condominium project.  In order to give Hugh the time needed to obtain necessary building permits, the contract provided for a closing (when the buyer pays and the seller delivers the deed) within one year after the contract was signed.  During the year, Hugh worked diligently to obtain all of the permits needed and he kept Norman advised of his efforts. However, he was unable to get the sewer permit in time and he suggested to Norman that they reschedule the closing for two weeks later.  Norman refused and said that the date in the contract was a firm date and if Hugh did not close by the date specified in the contract, he was breaching the contract.

Do you agree with Norman?  Why or why not?

Request for Solution File

Ask an Expert for Answer!!
Business Law and Ethics: Discussion about breaching the contract
Reference No:- TGS03417000

Expected delivery within 24 Hours