Discuss the final stage of the construction for garth road


Assignment task: CREATING A SECTIONAL DRAWING SANITARY DRAINAGE PIPE

Leading up to the final stage of the construction for Garth Road, you realise you are not going to make the completion date. The change of tiles that Mrs Jones requested took a long time to come in which delayed the completion of the bathroom tiling. This delayed the installation of the bathroom fixtures as the plumber started another job and HIA Construction had to wait for them to return. Due to this, HIA Construction will need to request an extension of 10 days. You are slightly concerned that this extension could result in a financial penalty but can't remember what was stipulated in the construction contract.

 