Discuss how much are they charging for the project


A company named Highway Data has been given a bond to install the highway information signs along a 500 mile portion of interstate 555. The signs will be placed at the end of each 10 mile section. The signs cost $138 each. Data fiber optic cable communication lines are also required which will cost $1,299 per mile for material and installation. There will also be a onetime cost of 9,629 to create a network connection through Verizon networking group. Highway Data will gain 32% profit on this project. Discuss how much are they charging for the project?