Discuss about a project networking


Discuss the below:

Details:

Project Networking provides the necessary tools to monitor project progress. Considerable time and effort is expended developing successful project networks.

Refer to exercise 9 in chapter 6 of the textbook. Read the assignment thoroughly and analyze the data provided in the diagram.

Compute the project network sequence and proper timing to complete the project using an excel spreadsheet, PowerPoint, or another appropriate form of delivery method. Address all required information in the description presented in exercise 9. In addition, answer to the following questions (300-500 words):

1. Provide the Early Start, Early Finish, Late Start, and Late Finish times for each activity. Compute the Total Slack for each activity.

Determine which activities are on the critical path. How long will it take to complete the project?

2. An activity that is on the critical path for this project has increased by 7. Will the project end date be delayed? If so, by how much?
APA format is not required, but solid academic writing is expected.

HERE IS EXERCISE 9 CHAPTER 6

9. You are creating a customer database for the Modesto Nuts minor league baseball team. Draw a project network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path.

How long will this project take? How sensitive is the network schedule?

Calculate the free slack and total slack for all noncritical activities.

Time

ID Description Predecessor (days)

A Systems design None 2

B Subsystem A design A 1

C Subsystem B design A 1

D Subsystem C design A 1

E Program A B 2

F Program B C 2

G Program C D 2

H Subsystem A test E 1

I Subsystem B test F 1

J Subsystem C test G 1

K Integration H, I, J 2

L Integration test K 1