Discuss a sample mean completion time


Discuss the below:

Q: A microwave manufacturing company has just switched to a new automated production system. Unfortunately, the new machinery has been frequently failing and requiring repairs and service. The company has been able to provide its customers with a completion time of 6 days or less. To analyze whether the completion time has increased, the production manager took a sample of 36 jobs and found that the sample mean completion time was 6.5 days with a sample standard deviation of 1.5 days. At a significance level of .10, test whether the completion time has increased.