Discrete math-structures


Assignment:

Q1. Determine the minimum time needed to complete your set of tasks.
Q2. Determine the Critical Path for your example. Explain what this gives you.
Q3. Comment on your example. Which task(s) cause a delay in the project? How would you fix the problem? Can you obtain more information out of your example?

Provide complete and step by step solution for the question and show calculations and use formulas.

Solution Preview :

Prepared by a verified Expert