Question - Hoopahup Toys Ltd. Produces a toy called the Rabbit. The company has recently established a standard cost system for Rabbit toy as follows:

Direct materials: 6 meters per Rabbit toy at $0.50 per meter.

Direct labour: 1.3 hours per Rabbit toy at $8 per hour.

During July, the company produced 3,000 units of Rabbit toys, and the production data for the month as follows:

Direct materials: 25,000 meters were purchased at a cost of $0.48 per meter. 5,000 of these meters were still in inventory at the end of the month.

Direct labour: 4,000 direct labour hours were worked at a cost of $36,000

Required:

1. Compute direct materials price and quantity variances.

2. Compute direct labour rate and efficiency variances.

3. Prepare a brief explanation of the possible causes of each variance.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Direct labour 4000 direct labour hours were worked at a
Reference No:- TGS02878974

Now Priced at $25 (50% Discount)

Recommended (92%)

Rated (4.4/5)