Develop the quarterly forecasts of power loads


Assignment:

The manager of a utility company in the Texas panhandle wants to develop quarterly forecasts of power loads for the next year. The power loads are seasonal, and the data on the quarterly loads in megawatts (MW) for the last four years are as follows:

Quarter   Year 1   Year 2   Year 3   Year 4
  1          102.3     96.6     120.7    104.1
  2          126.7     115.8   145.1     132.7 
  3          142.2     139.4   162.4     154.8
  4          164.4     156.2   183.7     169.0

The manager estimates the total demand for the next year at 727

MW. Use the multiplicative seasonal method to develop the forecast for each quarter. (Round all intermediate calculations to three decimal places.)

The first quarter forecast is ____MW.(Enter your response rounded to one decimal place.)