Develop the mixed model repeating sequence assuming 60


A schedule calls for producing 40 As, 20 Bs, and 30Cs. Process time is 5 minutes per A, 8 minutes per B, and 10 minutes per C.

a) Develop the mixed model repeating sequence. Assuming 60 seconds changeover between products, how long will the scheduled production take?

b) Assume no more than 700 minutes a day is available to produce these products. Suggest a way to reduce the required production time to meet this constraint.

Solution Preview :

Prepared by a verified Expert
Business Management: Develop the mixed model repeating sequence assuming 60
Reference No:- TGS02861529

Now Priced at $10 (50% Discount)

Recommended (97%)

Rated (4.9/5)