Q: Product A is comprised of 1 unit of X and 2 units of Y. X is made of 1 unit of M and 2 units of N. Y is made of 2 units of K and 3 units of L. A customer has ordered 500 units of A to be delivered in week 9. Lead times, on hand units and specific lot size requirements are as shown in the table below:

Item                         Lead Time (weeks)      On hand units              Lot sized requirements

A                                      1                       100

X                                     2                          250                            200

Y                                    3                          500                            400

M                                   2                                                            500

N                                   3                          100

K                                    2

L                                    1

Develop planning schedules for each item showing how much should be ordered and in what quantities.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Develop planning schedules for each item
Reference No:- TGS02056897

Expected delivery within 24 Hours