Develop an mrp planning schedule showing gross receipt dates


Questions:

Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and three of D. D is made of three units of E.

Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.

Seventy units OF Product Z are required in Period 10. (Assume that there is currently no inventory on hand of any of these items.)

Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates.

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: Develop an mrp planning schedule showing gross receipt dates
Reference No:- TGS01978136

Expected delivery within 24 Hours