Develop an mrp planning schedule showing gross and net


Assume that Product Z is made of two units of A and three units of B. A is made of four units of C and four of D. D is made of two units of E.

Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.

Fifty six units OF Product Z are required in Period 10. (Assume that there is currently no inventory on hand of any of these items.)

Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells blank - be certain to enter "0" wherever required.)

Hint: enter "0" for "Scheduled receipts" and "Projected available balance"

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Develop an mrp planning schedule showing gross and net
Reference No:- TGS02938323

Expected delivery within 24 Hours