Develop an estimate of variable electricity costs


Problem: Machine hours and electricity costs for Wells Industries for 2011 were as follows:

                        Machine        Electricity
Month                 Hours            Costs
January               2,000         $ 9,200
February              2,320          10,500
March                  1,520            6,750
April                    2,480           11,500
May                     3,040           14,125
June                    2,640            11,000
July                     3,280            12,375
August                 2,800            11,375
September           1,600             7,750
October                2,960           13,000
November             3,760           15,500
December              3,360           13,875

Required:

Q1. Using the high-low method, develop an estimate of variable electricity costs per machine hour.

Q2. Using the high-low method, develop an estimate of fixed electricity costs per month.

Q3. Using the high-low method,develop a cost function for monthly electricity costs.

Q4. Estimate electricity costs for a month in which 3,000 machine hours are worked.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Develop an estimate of variable electricity costs
Reference No:- TGS01918467

Now Priced at $25 (50% Discount)

Recommended (95%)

Rated (4.7/5)