Develop a material requirement plan for next weeks


Problem:

The MPS for product A calls for 100 units to be completed in week 4 and 200 units in week 7 (the lead time is 1 week). Spare part demand for Item B is 10 units per week. The bill of materials for product A is shown on the right, and the inventory records are as follows:

Item B:

Lot sizing rule: FOQ=500

Lead time (wks): 2

Beginning (on-hand) inventory: 100

Scheduled receipts: none

Item C:

Lot sizing rule: LFL

Lead time (wks): 3

Beginning (on-hand) inventory: 10

Scheduled receipts: 200 (week 2)

Required:

i) Develop a material requirement plan for the next 7 weeks for Item B and C.

ii) Will any action notices be generated? If so, explain what they are and why they must be generated.

Determine the solution of the given problem.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Develop a material requirement plan for next weeks