Develop a high-tech product in a short period of time


Problem

i. When completing the forward pass, the project duration is determined. A project duration of 45 days does not mean that if the project were to start today it would be complete in 45 days. Explain in no more than two lines.

ii. For a project that the main objective is to develop a high-tech product in a short period of time, would you hire a project manager with deep knowledge but limited experience working as project team member in related technology area or a project manager with a successful experience  in delivery of projects in another field of technology? Explain your reasonings in less than three lines.