Develop a gantt chart to determine the total time required


Question: In problem , assume there are two machines of type A and two of type B.

a. Prepare a finite capacity schedule.

b. How does your FCS compare to the performance of the Gantt chart in problem?

Problem: Six jobs must be processed through machine A and then machine B as shown below. The processing time for each job is also shown.

2277_Job.png

a. Develop a Gantt chart to determine the total time required to process all six jobs. Use the following sequence of jobs: 1, 2, 3, 4, 5, 6.

b. Can you develop a better sequence to reduce the total time required for processing?