Determining time for different amount of units


Assignment:

A certain electrical harness assembly job required 35.0 min to complete when a skilled worker did it the first time. The job will be performed to produce 100 harnesses. If the learning rate is 85%, what will the time be (a) for the 10th unit and (b) for the 100th unit?

Typical Learning Rates for Various Types of Work

Type of Work                                   Typical Learning Rate (%)

Assembly, electrical harness                                85

Assembly, electronic                                            85

Assembly, mechanical                                          84

Assembly of prototypes                                       65

Inspection                                                            86

Machining                                                           90-95

Sheet metal working                                            90

Welding                                                                85

Provide complete and step by step solution for the question and show calculations and use formulas.