Determining throughput for aisle under assumptions


Assignment:

The length of the storage aisle in an AS/RS = 240 ft and its height = 60 ft. Suppose horizontal and vertical speeds of the S/R machine are 300 ft/min and 60 ft/min, respectively. The S/R machine requires 18 sec to accomplish a pick-and-deposit operation. Find: (a) the single command and dual command cycle times per aisle and (b) throughput for the aisle under the assumptions that storage system utilization = 85% and the numbers of single command and dual command cycles arc equal.

Provide complete and step by step solution for the question and show calculations and use formulas.

Request for Solution File

Ask an Expert for Answer!!
Other Engineering: Determining throughput for aisle under assumptions
Reference No:- TGS01978221

Expected delivery within 24 Hours