Determining the net present value of the project


Question: The Wexler Company is considering the purchase of a new machine costing $250,000. This machine is estimated to cost $5,000 per year in operating expenses but it will allow the company to earn an additional $100,000 per year in revenues and at the end of 3 years the machine will have a salvage value of $40,000. If the required rate of return is 12% what is the net present value of this project? (Round the answer to the nearest whole dollar)