Determining the estimated amounts


Problem:

Lake Prairie Company uses a plantwide overhead rate with machine hours as the allocation base. Next year, 120,000 units are expected to be produced taking 0.80 machine hours each.

Required:

Question: How much overhead will be assigned to each unit produced given the following estimated amounts?

Note: Please provide step by step solution.

Estimated: Department 1 Department 2
  Manufacturing overhead costs $5,386,000 $2,457,000
  Direct hours     500,000 DLH 550,000 DLH
  Machine hours 340,000 MH     280,000 MH