Determining labor rate variance


Response to the following problem:

Verde Company produces wheels for bicycles. During the year, 330,000 wheels were produced. The actual labor used was 180,000 hours at $9.25 per hour. Verde has the following labor standard: 0.5 hour at $10.

Required:

1. Compute the labor rate variance.

2. Compute the labor efficiency variance.

 

Solution Preview :

Prepared by a verified Expert
Cost Accounting: Determining labor rate variance
Reference No:- TGS02075840

Now Priced at $20 (50% Discount)

Recommended (98%)

Rated (4.3/5)