Determining a labor and manufactured cost units


Assignment:

Problem

Johnson Industries received a contract to develop and produce four high-intensity long-distance receiver/transmitters for cellular telephone. The first took 2.200 labor hours and $40,000 worth of purchased and manufactured parts, the second took 1, 780 labor hours and $36, 400 in parts; the third took 1, 590 labor hours and $34, 400 in parts; and the fourth took 1,406 labor hours and $32, 400 in parts. Johnson was asked to bid on a follow-on contract for another dozen receiver/transmitters units.

a. How many labor hours should Johnson estimate are needed for the additional 12 units?

b. How much should Johnson estimate the parts cost will be for the additional 12 units?

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Determining a labor and manufactured cost units
Reference No:- TGS02083634

Expected delivery within 24 Hours