Determine utilization and efficiency of the work


A work center is composed of 3 machines staffed for two 8-hour shifts, 5 days a week. Thus, 240 work hours are available each week. Records for the past several weeks indicate that breakdowns reduced machine usage an indicate that the work center produced an average of 250.8 standard hours of output. Determine utilization and efficiency of the work center.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Determine utilization and efficiency of the work
Reference No:- TGS02878273