Determine the volume variance and controllable variance


Question: The standard factory overhead rate is $12 per machine hour ($10 for variable factory overhead and $2 for fixed factory overhead) based on 100% capacity of 42,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 2,000 units were as follows:

Actual: Variable factory overhead $350,500

Fixed factory overhead $84,000

Standard: 35,000 hours @$12 $420,000

Required - Determine the (a) volume variance, (b) controllable variance, and (c) total factory overhead cost variance.

Our Total Factory Overhead Cost Variance Assignment Help tutors work day and night and put their maximum effort, in order to make your assignment paper of the top quality.

Tags: Total Factory Overhead Cost Variance Assignment Help, Total Factory Overhead Cost Variance Homework Help, Total Factory Overhead Cost Variance Coursework, Total Factory Overhead Cost Variance Solved Assignments, Volume Variance Assignment Help, Volume Variance Homework Help, Controllable Variance Assignment Help, Controllable Variance Homework Help

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Determine the volume variance and controllable variance
Reference No:- TGS03041083

Expected delivery within 24 Hours