Determine the variance estimate of the activity


Problem:

You have determined the critical path in a CPM analysis. You would like to determine the probability of completing the project is a desired period of time. One of the activities on the critical path has an optimistic time of 5 minutes, a most likely time of 6, and a pessimistic time of 17.

Required:

Question 1) What is the variance estimate of this activity? Explain the solution in detail.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Determine the variance estimate of the activity
Reference No:- TGS0884681