Determine the value of equation curve application


Assignment:

In a learning curve application, 658.5 work hours are required for the third production unit and 615.7 work hours are required for the fourth production unit. Determine the value of n (and therefore s) in Equation (3-5).

Zu = K(un), (3-5)