Determine the transaction price for the contract


Assignment:

Q: Ivanhoe Corp. enters into a contract with a customer to build an apartment building for $1,013,300. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $152,100 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $50,700 each week that completion is delayed. Ivanhoe commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes:

Completed by
Probability
August 1, 2018
70 %
August 8, 2018
20
August 15, 2018
5
After August 15, 2018
5

(a) Determine the transaction price for the contract, assuming Ivanhoe is only able to estimate whether the building can be completed by August 1, 2018, or not (Ivanhoe estimates that there is a 70% chance that the building will be completed by August 1, 2018).

(b) Determine the transaction price for the contract, assuming Ivanhoe has limited information with which to develop a reliable estimate of completion by the August 1, 2018, deadline.

Request for Solution File

Ask an Expert for Answer!!
Basic Statistics: Determine the transaction price for the contract
Reference No:- TGS02034185

Expected delivery within 24 Hours