Determine the total estimated cost at completion and


Question: Determine the total estimated cost at completion and estimated cost to complete for the project in Problem I, assuming the cost performance index remains the same through the remainder of the job.

Problem I: The actual cost of the work performed at the end of the third week for the project in Problem II is $16,500. Determine the cost performance index for the project.

Problem II: A project consists of six tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 4. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is scheduled to begin at the start of Week 3 and end at the end of Week 4. Task D is scheduled to begin at the start of Week 1 and end at the end of Week 1. Task E is scheduled to begin at the start of Week 2 and end at the end of Week 4. Task F is scheduled to begin at the start of Week 4 and end at the end of Week 4. The budgeted cost for Task A is $10,000, for Task B is $2,000, for Task C is $3,000, for Task D is $1,000, for Task E is $6,000, and for Task F is $4,000. At the end of the third week Task A is 80% complete, Task B is 100% complete, Task C is 40% complete, Task D is 100% complete, Task E is 55% complete, and Task F has not started. What is the schedule performance index for the project at the end of the third week?

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Determine the total estimated cost at completion and
Reference No:- TGS02313391

Expected delivery within 24 Hours