Determine the spi and cpi


Project has just completed 87th item in its action plan. It was scheduled to have spent $168,000 at this point in plan, but has actually spent only $156,000. Foreman evaluates that value of work actually finished is about $162,000. Write down the spending and schedule variances for project? Determine the SPI and CPI?