Determine the score for each alternative


Problem: Project Processes

Activity 1: Three new-product ideas have been suggested. These ideas have been rated as shown in the Table below Product* CriteriaABCWeight (%)Development costPFVG10Sales prospectsVGEG15ProducibilityPFG10Competitive advantageEVGF15Technical riskPFVG20Patent protectionFFVG10Compatibility with strategyVGFF20 100* P = poor, F = fair, G = good, VG = very good, E = excellent

a. Using an equal point spread for all five ratings (i.e., P = 1 , F = 2 , G = 3 , VG = 4 , E = 5 P=1, F=2, G=3, VG=4, E=5), determine a weighted score for each product idea. What is the ranking of the three products?

b. Rank the criteria, compute the rank-sum weights, and determine the score for each alternative. Do the same using the rank reciprocal weights.

c. What are some of the advantages and disadvantages of this method of product selection?.

Activity 2: Using MAUT and the AHP, perform an analysis to select a graduate program. Explain your assumptions and indicate which technique you believe is most appropriate for this application.

Textbook: Project Management by SHTUB, 3RD Edition. ISBN: 9780134478661.

The response must include a reference list. Using Times New Roman 12 pnt font, double-space, one-inch margins, and APA style of writing and citations.

Solution Preview :

Prepared by a verified Expert
Project Management: Determine the score for each alternative
Reference No:- TGS03135110

Now Priced at $25 (50% Discount)

Recommended (98%)

Rated (4.3/5)