The project manager is paid $30/hour and each primary (P) worker is paid $25/hour while support (S) workers are paid $15/hour.

1. Determine the project's total labor costs. Explain your results. Submit a copy of your Resource Sheet.

2. When developing the project cost plan, what things should be considered to estimate the total project costs? It may be helpful to contact actual contractors, construction companies, vendors, etc., for the tasks involved in this type of project.

Extra information:

                                                Primary                        Support

Activity                                    Responsibility             Responsibility

Roof                                           Jack                      Steve, Wally

HVAC                                          Bill                       Scott, Trevor

Landscaping                                 John                       Lynn, Beth

Paving                                         Greg                         Jeff, Pat

Plumbing                                      Max                     Tyler, Damian

Grading and Site Prep                     Sal                           Jim, Joe

Interior Structure                          Don                     Keith, Andrea

Foundation Construction                 Randy                     Mark, Mike

Exterior Structure                          Bob                         Dan, Ken

Electrical                                      Seth                         Neil, Roy

It takes 30 days (standard 8-hour workdays, Monday through Friday) to complete each activity.