Determine the processing sequence at the first work center


Assignment:

Q: The following table shows orders to be processed at a machine shop as of 8:00 a.m. Monday. The jobs have different operations they must go through. Processing times are in days. Jobs are listed in order of arrival.

Job Processing
Time (Days)
Due Date
(Days)
Remaining Number
of Operations
A 8         20 2
B 10         18 4
C 5         25 5
D 11         17 3
E 9         35 4

a. Determine the processing sequence at the first work center using each of these rules:

(1) First come, first served,

(2) Slack per operation.

b. Compute the effectiveness of each rule using each of these measures: (1) average completion time, (2) average number of jobs at the work center.

Request for Solution File

Ask an Expert for Answer!!
Other Subject: Determine the processing sequence at the first work center
Reference No:- TGS02053579

Expected delivery within 24 Hours