Determine the percentage of revenue


Response to the following problem:

Contract for new administration building

Total Contract Amount $ 60,000,000. Contract Grant Date August 14, 2012. Construction Began September 1, 2012.

Estimated Cost to Complete at beginning of contract $ 52,000,000

Estimated Time to Complete Project 2 years As of Dec 31, 2012

Construction Costs incurred to date $ 14,140,000

Billings to date $ 19,500,000

Expected costs to complete $ 36,360,000

The Pickle construction division was working on one project for the 2012 fiscal year. They use the percentage of completion revenue recognition method.