Problem: Georgia Pacific offers the following discount schedule for its 4X8 ft. sheets of quality plywood.

Order

Unit Cost ($)

Less than 100 sheets

18.00

100 to 499 sheets

17.50

500 to 750 sheets

17.25

More than 750 sheets

17.00

Ace Lumber and Building Supply regularly stocks this product from Georgia pacific and has an annual demand of 1000 sheets. The carrying cost at Ace Lumber is 20% of product cost, and a cost of $45 is incurred with each order.

a) Determine the optimal order quantity for Ace Lumber.