Determine the minimum number of stations for the above


Determine the minimum number of stations for the above assembly line balancing problem by using the “Ranked Positional Weight” procedure for a Cycle Time of 12 minutes.                                         

Note: Determine SEi, LE, monthly output rate [22 days, 2 shifts, 8 hours/day].

Clearly indicate what operations are assigned to each station.