A production line with 12 tasks has the precedence relationships and durations presented in the following table. The line runs 8 hours a day and has a daily demand of 80 products, but a demand reduction is anticipated that will reduce demand to half its current level.

                                   Duration
Task       Precedence       (min)
A                -                  6
B                -                  9
C                A                 4
D                A                 5
E                B                 4
F                C                 2
G              C,D                3
H               F                 7
I                G                 3
J               E,I                1
K              H,J               10
K               K                 1

1. Draw the line balance in order to minimize the number of workstations according to the largest-positional-weight heuristic.

2. Determine the total idle time, the lead time, and the work-in process.

3. Make a sketch of the cell layout indicating what tasks will be carried out in each station by the assigned workers.